Guest Blog: Lapsed MahaRERA Registration Of 388 Projects In 2021 Impacts 20,955 Units

Guest Blog: Lapsed MahaRERA Registration Of 388 Projects In 2021 Impacts 20,955 Units

Guest Blog: Lapsed MahaRERA Registration Of 388 Projects In 2021 Impacts 20,955 Units

Anarock-property-consultants

MahaRERA’s recently released list of 407 projects that ‘lapsed’ in 2021 across the state of Maharashtra includes 388 residential and 19 commercial projects. ANAROCK Research’s deep dive into the data reveals that the 388 of these lapsed projects account for approx. 20,955 housing units, of which 52% (approx. 10,682 units) are already sold. The remaining 10,093 units remain unsold.

The top 5 cities in the state with the maximum lapsed projects are MMR, Pune, Aurangabad, Nagpur, and Satara, respectively.

  • MMR has the maximum number of ‘lapsed’ residential projects – 145 projects accounting for approx. 9,236 units, of which approx. 5,983 units or 65% are sold while 3,253 units are unsold
  • Pune has at least 92 lapsed housing projects comprising 4,852 units, of which 2,488 or approx. 51% units are sold, with 2,364 units remaining unsold
  • In Aurangabad, the registration numbers of 27 housing projects have expired. There are approx. 1,116 units in these projects, of which 254 units (23%) are sold while 862 units remain unsold
  • In Nagpur, approx. 23 housing projects account for 1,392 units, of which 777 or approx. 56% units are sold while the remaining 615 are unsold
  • In Satara, RERA registration has lapsed for 23 housing projects comprising 1,664 units, of which 661 or approx. 40% units are sold while 1,003 remain unsold.

What Lies Beneath

Santhosh Kumar, Vice Chairman – ANAROCK Group, said, “The RERA registration numbers of these projects lapsed for several reasons. RERA was implemented in 2017, and a year later the IL&FS crisis held real estate – particularly the residential segment – hostage. NBFCs were a major funding source for the real estate industry, with banks reluctant due to rising NPAs. NBFC funding slowed down significantly with the IL&FS crisis.”

Private equity funding into the sector also slowed down to a trickle as PE players became skittish and hyper-sensitive to market signals and began exercising immense caution before lending to developers. Grade B and C developers were the most impacted as lending to them was minimal, so the construction of various projects was impacted.

Just as funding issues began to get resolved, the pandemic worsened the situation for medium to small players due to disruptions in demand, and the supply of raw materials. In the last two years, buyers have been heavily favoring branded projects; medium-to-small players took the biggest hit, with their projects now accounting for most on the list of lapsed RERA registrations.

“Fortunately, Government-backed funds are now identifying projects that are near to completion, and providing last-mile funding,” said Santhosh Kumar. “Also, some of the larger developers are taking over and reviving other smaller projects” added Kumar.

About the author- Santhosh Kumar, Vice Chairman – ANAROCK Group

Leave a Reply

Your email address will not be published. Required fields are marked *